NVE-Company OB
200 MW hybrid in Churchill, NV · In queue since September 2022 · Proposed COD December 2030
200 MW
Capacity
1
Components
Solar
3y 8m
In Queue
Suspended
IA Status
COD target: 2030
Total Duration
8y 3m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-12-31
The NVE-Company OB development project is a proposed 200 MW solar and battery hybrid project located in Churchill County, Nevada. The project consists of 200 MW of solar generation, coupled with battery storage. It is listed in the NV Energy interconnection queue as of September 29, 2022, with a proposed commercial operation date of December 31, 2030.
The project's interconnection status is currently listed as suspended, and its interconnection agreement (IA) status is also suspended.
Generated from interconnection queue and public data sources
State
NV
County
Churchill
Grid Region
Mountain West
Market
—
Developer
—
Utility
NV Energy
Entity
NVE
Service Type
—
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project NVE-Company OB