NVE-Company OI
380 MW hybrid in Esmeralda, NV · In queue since January 2023 · Proposed COD December 2026
380 MW
Capacity
1
Components
Solar
3y 4m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
3y 11m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-01
The NVE-Company OI project is a proposed 380 MW hybrid solar and battery energy storage project located in Esmeralda County, Nevada. The project, developed by NVE, consists of 380 MW of solar photovoltaic generation. It is currently active in the NV Energy interconnection queue, with an entry date of January 9, 2023, and a proposed commercial operation date of December 1, 2026.
The project's interconnection agreement status is listed as "In Progress (unknown study)". The NVE-Company OI project is located in the Western region of the United States. It has appeared in recent news coverage regarding renewable energy development in Nevada.
Generated from interconnection queue and public data sources
State
NV
County
Esmeralda
Grid Region
Mountain West
Market
—
Developer
—
Utility
NV Energy
Entity
NVE
Service Type
—
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project NVE-Company OI