NVE-Company OQ
500 MW hybrid in Lander, NV · In queue since January 2023 · Proposed COD December 2035
500 MW
Capacity
1
Components
Solar
3y 4m
In Queue
Suspended
IA Status
COD target: 2035
Total Duration
12y 11m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2035-12-31
The proposed NVE-Company OQ project is a 500 MW hybrid solar and battery energy storage development in Lander County, Nevada. Interconnecting to NV Energy, the project entered the NVE interconnection queue on January 10, 2023, with a proposed commercial operation date of December 31, 2035. The interconnection agreement is currently suspended.
The project consists of 500 MW of solar photovoltaic generation paired with battery storage. The project's interconnection status is listed as suspended. Recent news coverage has discussed the project's progress and potential impact on the region's energy landscape.
Generated from interconnection queue and public data sources
State
NV
County
Lander
Grid Region
Mountain West
Market
—
Developer
—
Utility
NV Energy
Entity
NVE
Service Type
—
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.