Project NVE-Company OW — Project Summary

Queue ID
NVE-Company OW
Capacity
500 MW
Technology
Battery
Status
suspended
Location
Lyon, NV
Region
West
Developer
IA Status
Suspended

NVE-Company OW

NVE-Company OWBetaSuspendedBatteryNVELBNL

500 MW storage in Lyon, NV · In queue since January 2023 · Proposed COD November 2028

500 MW

Capacity

1

Components

Battery

3y 4m

In Queue

Suspended

IA Status

COD target: 2028

Interconnection

Total Duration

5y 10m

Suspended38%
Queue EntryJan 17, 2023

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-11-01

About

The NVE-Company OW project is a proposed 500 MW battery storage development in Lyon County, Nevada. The project, located in the western region of the United States, is being developed by NV Energy (NVE). It consists of a single 500 MW battery component.

The project is currently in the NV Energy interconnection queue with a queue entry date of January 17, 2023. The proposed commercial operation date is November 1, 2028. The interconnection agreement status is currently listed as suspended. The project has appeared in recent news coverage.

Generated from interconnection queue and public data sources

Project Details

State

NV

County

Lyon

Grid Region

Mountain West

Market

Developer

Utility

NV Energy

Entity

NVE

Service Type

Data Source

LBNL

Market Context
Approximate
ISO / RTO
MOUNTAIN_WEST
Trading Hub
PALOVERDE
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project NVE-Company OW