NVE-Company OX
500 MW hybrid in Lyon, NV · In queue since January 2023 · Proposed COD November 2028
500 MW
Capacity
1
Components
Solar
3y 4m
In Queue
Suspended
IA Status
COD target: 2028
Total Duration
5y 10m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-11-01
The NVE-Company OX development project is a proposed 500 MW solar and battery hybrid project located in Lyon County, Nevada. The project, under consideration by NV Energy, consists of 500 MW of solar capacity.
The project is currently in the NV Energy interconnection queue as of January 17, 2023, with a proposed commercial operation date of November 1, 2028. Its interconnection agreement status is currently listed as suspended.
Generated from interconnection queue and public data sources
State
NV
County
Lyon
Grid Region
Mountain West
Market
—
Developer
—
Utility
NV Energy
Entity
NVE
Service Type
—
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.