NVE-Company OY
500 MW storage in Lyon, NV · In queue since January 2023 · Proposed COD November 2028
500 MW
Capacity
1
Components
Battery
3y 4m
In Queue
Suspended
IA Status
COD target: 2028
Total Duration
5y 10m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-11-01
The NVE-Company OY project is a proposed 500 MW battery storage project located in Lyon County, Nevada. The project, developed by NVE, entered the NV Energy interconnection queue on January 17, 2023, with a proposed commercial operation date of November 1, 2028. Its interconnection agreement status is currently listed as suspended.
The project consists of 500 MW of battery storage capacity. The project's status in the interconnection queue is also listed as suspended.
Generated from interconnection queue and public data sources
State
NV
County
Lyon
Grid Region
Mountain West
Market
—
Developer
—
Utility
NV Energy
Entity
NVE
Service Type
—
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.