NVE-Company QK
38.5 MW generation in Lyon, NV · In queue since September 2023 · Proposed COD May 2030
38.5 MW
Capacity
1
Components
Geothermal
2y 8m
In Queue
IA Executed
IA Status
COD target: 2030
Total Duration
6y 8m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–36 months
Proposed COD: 2030-05-30
NVE-Company QK is a proposed geothermal generation project with a total capacity of 38.5 MW, located in Lyon County, Nevada. The project is being developed by NVE and is interconnected with NV Energy. It entered the NV Energy interconnection queue on September 28, 2023, and has a proposed commercial operation date of May 30, 2030.
The project's interconnection agreement has been executed. Recent news coverage of the project is available.
Generated from interconnection queue and public data sources
State
NV
County
Lyon
Grid Region
Mountain West
Market
—
Developer
—
Utility
NV Energy
Entity
NVE
Service Type
—
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project NVE-Company QK