NVE-Company QX
240 MW hybrid in Churchill, NV · In queue since March 2024 · Proposed COD November 2028
240 MW
Capacity
1
Components
Solar
2y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2028
Total Duration
4y 8m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-11-15
NVE-Company QX is a proposed 240 MW solar and battery hybrid project located in Churchill County, Nevada. The development project consists of 240 MW of solar generation capacity. It is listed in the NV Energy interconnection queue as of March 28, 2024, with a proposed commercial operation date of November 15, 2028. The project's interconnection agreement status is currently "In Progress (unknown study)".
The project is sponsored by NVE. It is located in the Western region of the United States. The proposed project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
NV
County
Churchill
Grid Region
Mountain West
Market
—
Developer
—
Utility
NV Energy
Entity
NVE
Service Type
—
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.