NWMT-300
315 MW hybrid in Stillwater, MT · In queue since July 2016 · Proposed COD August 2020
315 MW
Capacity
1
Components
Wind
9y 10m
In Queue
Facility Study
IA Status
COD target: 2020
Total Duration
4y 1m
Schedule
70 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2020-08-15
The NWMT-300 development project is a proposed 315 MW hybrid wind and battery project located in Stillwater County, Montana. Interconnecting to NorthWestern Energy via the 230kV line between the Wilsall and Columbus Rapelje Substations, the project entered the NWMT interconnection queue on July 11, 2016. The proposed commercial operation date is August 15, 2020, and the project's interconnection agreement status is currently in the Facility Study phase.
The hybrid project consists of 315 MW of wind generation capacity. The project has appeared in recent news coverage regarding renewable energy development in the region.
Generated from interconnection queue and public data sources
State
MT
County
Stillwater
Grid Region
Mountain West
Market
—
Developer
—
Utility
NorthWestern Energy
Entity
NWMT
Service Type
—
Point of Interconnection
230kV Line between Wilsall and Columbus Rapelje Substations
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project NWMT-300