NWMT-310
450 MW storage in Meagher, MT · In queue since December 2016 · Proposed COD February 2023
450 MW
Capacity
1
Components
Other Storage
9y 5m
In Queue
Facility Study
IA Status
COD target: 2023
Total Duration
6y 2m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-02-01
The proposed NWMT-310 project is a 450 MW battery storage development in Meagher County, Montana. Interconnection is with NorthWestern Energy (NWMT) in the West region. The project entered the interconnection queue on December 21, 2016, with a proposed commercial operation date of February 1, 2023. Its interconnection status is currently in the Facility Study phase.
The project consists of 450 MW of "Other Storage" technology. The point of interconnection is at a new 500kV substation between Broadview and Townsend. The project's status is currently listed as suspended.
Generated from interconnection queue and public data sources
State
MT
County
Meagher
Grid Region
Mountain West
Market
—
Developer
—
Utility
NorthWestern Energy
Entity
NWMT
Service Type
—
Point of Interconnection
New 500kV Substation between Broadview and Townsend
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project NWMT-310