NWMT-335
80 MW hybrid in Wheatland, MT · In queue since September 2017 · Proposed COD October 2024
80 MW
Capacity
1
Components
Wind
8y 8m
In Queue
Facility Study
IA Status
COD target: 2024
Total Duration
7y 1m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-10-31
The proposed NWMT-335 project is an 80 MW hybrid wind and battery energy storage development in Wheatland County, Montana. Interconnection is requested with NorthWestern Energy via the NWMT queue, with an initial queue entry date of September 25, 2017. The project consists of 80 MW of wind generation capacity.
The proposed commercial operation date is October 31, 2024. The project's interconnection status is currently in the Facility Study phase, but is listed as suspended in the interconnection queue. The point of interconnection is the 230kV line from Judith Gap Auto to Judith Gap South.
Generated from interconnection queue and public data sources
State
MT
County
Wheatland
Grid Region
Mountain West
Market
—
Developer
—
Utility
NorthWestern Energy
Entity
NWMT
Service Type
—
Point of Interconnection
230kV Line from Judith Gap Auto to Judith Gap South
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.