NWMT-340
20 MW hybrid in Yellowstone, MT · In queue since March 2018 · Proposed COD June 2021
20 MW
Capacity
1
Components
Solar
8y 2m
In Queue
Facility Study
IA Status
COD target: 2021
Total Duration
3y 3m
Schedule
60 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2021-06-01
The proposed NWMT-340 project is a 20 MW solar and battery hybrid development in Yellowstone County, Montana. Interconnecting to NorthWestern Energy via the 161kV line at Alkali Creek Substation, the project consists of 20 MW of solar capacity.
The project is listed in the NWMT interconnection queue with an entry date of March 5, 2018. Its proposed commercial operation date is June 1, 2021, and its interconnection status is currently in the Facility Study phase.
Generated from interconnection queue and public data sources
State
MT
County
Yellowstone
Grid Region
Mountain West
Market
—
Developer
—
Utility
NorthWestern Energy
Entity
NWMT
Service Type
—
Point of Interconnection
161kV line at Alkali Creek Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project NWMT-340