NWMT-358
80 MW hybrid in Yellowstone, MT · In queue since October 2018 · Proposed COD December 2022
80 MW
Capacity
1
Components
Solar
7y 7m
In Queue
Facility Study
IA Status
COD target: 2022
Total Duration
4y 2m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2022-12-31
The proposed NWMT-358 project is an 80 MW solar and battery hybrid development in Yellowstone County, Montana. The project, located in the western United States and interconnected with NorthWestern Energy (NWMT), consists of 80 MW of solar generation. It entered the interconnection queue on October 11, 2018, with a proposed commercial operation date of December 31, 2022.
The project's interconnection status is currently listed as "suspended" and is in the Facility Study phase. The point of interconnection (POI) is the 230kV Broadview Substation.
Generated from interconnection queue and public data sources
State
MT
County
Yellowstone
Grid Region
Mountain West
Market
—
Developer
—
Utility
NorthWestern Energy
Entity
NWMT
Service Type
—
Point of Interconnection
230kV at Broadview Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project NWMT-358