NWMT-360
200 MW generation in Wheatland, MT · In queue since February 2019 · Proposed COD December 2021
200 MW
Capacity
1
Components
Wind
7y 3m
In Queue
System Impact Study
IA Status
COD target: 2021
Total Duration
2y 10m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2021-12-31
The NWMT-360 development project is a proposed 200 MW wind generation facility in Wheatland County, Montana. The project, located in the West region, is being proposed within the NorthWestern Energy (NWMT) service area. It entered the NWMT interconnection queue on February 14, 2019, with a proposed commercial operation date of December 31, 2021.
The project's interconnection status is currently in the System Impact Study phase. The point of interconnection (POI) is planned for the 230kV line at Judith Gap Auto. The project's status is currently listed as suspended.
Generated from interconnection queue and public data sources
State
MT
County
Wheatland
Grid Region
Mountain West
Market
—
Developer
—
Utility
NorthWestern Energy
Entity
NWMT
Service Type
—
Point of Interconnection
230kV at Judith Gap Auto
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project NWMT-360