NWMT-361
600 MW generation in Wheatland, MT · In queue since March 2019 · Proposed COD December 2021
600 MW
Capacity
1
Components
Wind
7y 2m
In Queue
Facility Study
IA Status
COD target: 2021
Total Duration
2y 9m
Schedule
53 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2021-12-31
The NWMT-361 project is a proposed 600 MW wind generation project located in Wheatland County, Montana. The project is listed in the NorthWestern Energy (NWMT) interconnection queue with an entry date of March 15, 2019. The proposed commercial operation date is December 31, 2021.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is a new proposed 500kV Substation between Broadview and Townsend.
Generated from interconnection queue and public data sources
State
MT
County
Wheatland
Grid Region
Mountain West
Market
—
Developer
—
Utility
NorthWestern Energy
Entity
NWMT
Service Type
—
Point of Interconnection
New proposed 500kV Substation between Broadview and Townsend
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project NWMT-361