NWMT-362
300.15 MW generation in Wheatland, MT · In queue since April 2019 · Proposed COD October 2022
300.15 MW
Capacity
1
Components
Wind
7y 1m
In Queue
Facility Study
IA Status
COD target: 2022
Total Duration
3y 6m
Schedule
43 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2022-10-31
The proposed NWMT-362 project is a 300.15 MW wind generation facility located in Wheatland County, Montana. Interconnection is with NorthWestern Energy (NWMT) in their interconnection queue, with an entry date of April 24, 2019. The proposed commercial operation date is October 31, 2022.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is a new proposed 500kV Substation between Broadview and Townsend. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
MT
County
Wheatland
Grid Region
Mountain West
Market
—
Developer
—
Utility
NorthWestern Energy
Entity
NWMT
Service Type
—
Point of Interconnection
New proposed 500kV Substation between Broadview and Townsend
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.