Project NWMT-375 — Project Summary

Queue ID
NWMT-375
Capacity
200 MW
Technology
Solar+Battery
Status
suspended
Location
Deer Lodge, MT
Region
West
Developer
IA Status
Feasibility Study

NWMT-375

NWMT-375BetaSuspendedSolarBatteryNWMTLBNL

200 MW hybrid in Deer Lodge, MT · In queue since March 2020 · Proposed COD February 2023

200 MW

Capacity

1

Components

Solar

6y 2m

In Queue

Feasibility Study

IA Status

COD target: 2023

Interconnection

Total Duration

2y 11m

Suspended13%
Queue EntryMar 19, 2020

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2023-02-01

About

The proposed NWMT-375 project is a 200 MW solar and battery hybrid development in Deer Lodge County, Montana. Interconnecting to NorthWestern Energy via the 230kV Anaconda Mill Creek Substation, the project consists of 200 MW of solar capacity.

The project entered the NWMT interconnection queue on March 19, 2020, with a proposed commercial operation date of February 1, 2023. Its interconnection status is currently in the Feasibility Study phase. The project's status is listed as suspended.

Generated from interconnection queue and public data sources

Project Details

State

MT

County

Deer Lodge

Grid Region

Mountain West

Market

Developer

Utility

NorthWestern Energy

Entity

NWMT

Service Type

Point of Interconnection

230kV at Anaconda Mill Creek Substation

Data Source

LBNL

Market Context
Approximate
ISO / RTO
MOUNTAIN_WEST
Trading Hub
MID-C
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project NWMT-375