NWMT-375
200 MW hybrid in Deer Lodge, MT · In queue since March 2020 · Proposed COD February 2023
200 MW
Capacity
1
Components
Solar
6y 2m
In Queue
Feasibility Study
IA Status
COD target: 2023
Total Duration
2y 11m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-02-01
The proposed NWMT-375 project is a 200 MW solar and battery hybrid development in Deer Lodge County, Montana. Interconnecting to NorthWestern Energy via the 230kV Anaconda Mill Creek Substation, the project consists of 200 MW of solar capacity.
The project entered the NWMT interconnection queue on March 19, 2020, with a proposed commercial operation date of February 1, 2023. Its interconnection status is currently in the Feasibility Study phase. The project's status is listed as suspended.
Generated from interconnection queue and public data sources
State
MT
County
Deer Lodge
Grid Region
Mountain West
Market
—
Developer
—
Utility
NorthWestern Energy
Entity
NWMT
Service Type
—
Point of Interconnection
230kV at Anaconda Mill Creek Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.