NWMT-377
36 MW generation in Silver Bow, MT · In queue since May 2020 · Proposed COD July 2022
36 MW
Capacity
1
Components
Gas
6 years
In Queue
System Impact Study
IA Status
COD target: 2022
Total Duration
2y 2m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2022-07-01
NWMT-377 is a proposed 36 MW gas-fired generation project located in Silver Bow County, Montana. The project is in the NorthWestern Energy (NWMT) interconnection queue, with an entry date of May 7, 2020. Its proposed commercial operation date is July 1, 2022. The interconnection request is currently in the System Impact Study phase.
The project's point of interconnection (POI) is the 161kV line at MHD. The project's status is currently listed as suspended.
Generated from interconnection queue and public data sources
State
MT
County
Silver Bow
Grid Region
Mountain West
Market
—
Developer
—
Utility
NorthWestern Energy
Entity
NWMT
Service Type
—
Point of Interconnection
161kV at MHD
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project NWMT-377