NWMT-391
750 MW generation in — · In queue since August 2020 · Proposed COD October 2023
750 MW
Capacity
1
Components
Wind
5y 9m
In Queue
Facility Study
IA Status
COD target: 2023
Total Duration
3y 2m
Schedule
31 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-10-31
NWMT-391 is a proposed 750 MW wind generation project located in an unspecified county in Montana. The project is being developed within the NorthWestern Energy (NWMT) service area. It consists of 750 MW of wind capacity.
The project is currently active in the NWMT interconnection queue with an entry date of August 26, 2020. The proposed commercial operation date is October 31, 2023. The project's interconnection status is currently in the Facility Study phase, and the point of interconnection is a new proposed 500kV Substation between Broadview and Townsend.
Generated from interconnection queue and public data sources
State
—
County
—
Grid Region
Mountain West
Market
—
Developer
—
Utility
NorthWestern Energy
Entity
NWMT
Service Type
—
Point of Interconnection
New proposed 500kV Substation between Broadview and Townsend
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project NWMT-391