NWMT-401
70 MW generation in Musselshell, MT · In queue since January 2021 · Proposed COD November 2023
70 MW
Capacity
1
Components
Wind
5y 4m
In Queue
Facility Study
IA Status
COD target: 2023
Total Duration
2y 10m
Schedule
30 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-11-15
NWMT-401 is a proposed 70 MW wind generation project located in Musselshell County, Montana. The project is listed in the NorthWestern Energy (NWMT) interconnection queue with an entry date of January 15, 2021. The proposed commercial operation date is November 15, 2023.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the 100kV Roundup Substation.
Generated from interconnection queue and public data sources
State
MT
County
Musselshell
Grid Region
Mountain West
Market
—
Developer
—
Utility
NorthWestern Energy
Entity
NWMT
Service Type
—
Point of Interconnection
100kV Roundup Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project NWMT-401