NWMT-406
300 MW generation in Rosebud, MT · In queue since February 2021 · Proposed COD December 2024
300 MW
Capacity
1
Components
Wind
5y 3m
In Queue
Facility Study
IA Status
COD target: 2024
Total Duration
3y 10m
Schedule
16 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-12-31
NWMT-406 is a proposed wind generation project with a total capacity of 300 MW. The development is located in Rosebud County, Montana, and is being managed within the NorthWestern Energy (NWMT) service area. The project's point of interconnection is the Colstrip 500kV Substation.
The project is currently active in the NWMT interconnection queue, with an entry date of February 2, 2021. The proposed commercial operation date is December 31, 2024. Its interconnection agreement status is currently in the Facility Study phase.
Generated from interconnection queue and public data sources
State
MT
County
Rosebud
Grid Region
Mountain West
Market
—
Developer
—
Utility
NorthWestern Energy
Entity
NWMT
Service Type
—
Point of Interconnection
Colstrip 500kV Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project NWMT-406