NWMT-408
326.25 MW generation in Wheatland, MT · In queue since February 2021 · Proposed COD December 2024
326.25 MW
Capacity
1
Components
Wind
5y 3m
In Queue
Facility Study
IA Status
COD target: 2024
Total Duration
3y 10m
Schedule
16 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-12-31
The proposed NWMT-408 project is a 326.25 MW wind generation facility located in Wheatland County, Montana. The project is listed in the NorthWestern Energy (NWMT) interconnection queue with an entry date of February 4, 2021, and a proposed commercial operation date of December 31, 2024. Its interconnection point is a new proposed 500kV Substation between Broadview and Townsend.
The project's interconnection status is currently in the Facility Study phase.
Generated from interconnection queue and public data sources
State
MT
County
Wheatland
Grid Region
Mountain West
Market
—
Developer
—
Utility
NorthWestern Energy
Entity
NWMT
Service Type
—
Point of Interconnection
New proposed 500kV Substation between Broadview and Townsend
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project NWMT-408