NWMT-412
80 MW hybrid in Gallatin, MT · In queue since June 2021
80 MW
Capacity
1
Components
Solar
4y 11m
In Queue
Facility Study
IA Status
Total Duration
4y 11m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
The proposed NWMT-412 project is an 80 MW solar and battery hybrid development in Gallatin County, Montana. Interconnecting to NorthWestern Energy via the Three Rivers 161kV Substation, the project entered the NWMT interconnection queue on June 1, 2021. Its interconnection status is currently in the Facility Study phase.
The project consists of 80 MW of solar generation co-located with battery storage. The proposed commercial operation date is not available. The project's status is currently listed as suspended.
Generated from interconnection queue and public data sources
State
MT
County
Gallatin
Grid Region
Mountain West
Market
—
Developer
—
Utility
NorthWestern Energy
Entity
NWMT
Service Type
—
Point of Interconnection
Three Rivers 161kV Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project NWMT-412