NWMT-417
50 MW hybrid in Wheatland, MT · In queue since November 2021 · Proposed COD December 2022
50 MW
Capacity
1
Components
Solar
4y 6m
In Queue
Facility Study
IA Status
COD target: 2022
Total Duration
1y 1m
Schedule
41 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2022-12-31
NWMT-417 is a proposed 50 MW hybrid solar and battery project located in Wheatland County, Montana. The project consists of 50 MW of solar capacity. It is listed in the NorthWestern Energy (NWMT) interconnection queue with an entry date of November 19, 2021. The proposed commercial operation date is December 31, 2022. The project's interconnection status is currently in the Facility Study phase, and the point of interconnection is the 230 kV line between Harlowton and Judith Gap.
The development project is in the West region and is classified as a hybrid project due to its combination of solar and battery technologies. Recent news coverage indicates public interest in the project's potential impact on the local energy grid.
Generated from interconnection queue and public data sources
State
MT
County
Wheatland
Grid Region
Mountain West
Market
—
Developer
—
Utility
NorthWestern Energy
Entity
NWMT
Service Type
—
Point of Interconnection
230 kV line between Harlowton and Judith Gap
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.