Project NWMT-418 — Project Summary

Queue ID
NWMT-418
Capacity
750 MW
Technology
Wind
Status
active
Location
Wheatland, MT
Region
West
Developer
IA Status
System Impact Study

NWMT-418

NWMT-418BetaActiveWindNWMTLBNL

750 MW generation in Wheatland, MT · In queue since January 2022 · Proposed COD October 2026

750 MW

Capacity

1

Components

Wind

4y 4m

In Queue

System Impact Study

IA Status

COD target: 2026

Interconnection

Total Duration

4y 9m

Impact Study25%
Queue EntryJan 10, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-10-31

About

The proposed NWMT-418 project is a 750 MW wind generation project located in Wheatland County, Montana. Interconnecting to NorthWestern Energy, the project entered the NWMT interconnection queue on January 10, 2022, with a proposed commercial operation date of October 31, 2026. The point of interconnection is a new proposed 500kV Substation between Broadview and Townsend.

The project's interconnection status is currently in the System Impact Study phase. The developer is listed as NWMT.

Generated from interconnection queue and public data sources

Project Details

State

MT

County

Wheatland

Grid Region

Mountain West

Market

Developer

Utility

NorthWestern Energy

Entity

NWMT

Service Type

Point of Interconnection

New proposed 500kV Substation between Broadview and Townsend

Data Source

LBNL

Market Context
Approximate
ISO / RTO
MOUNTAIN_WEST
Trading Hub
MID-C
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.