NWMT-431
50 MW hybrid in Wheatland, MT · In queue since September 2022 · Proposed COD December 2024
50 MW
Capacity
1
Components
Solar
3y 8m
In Queue
Facility Study
IA Status
COD target: 2024
Total Duration
2y 3m
Schedule
16 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-12-31
The proposed NWMT-431 project is a 50 MW hybrid solar and battery energy storage development in Wheatland County, Montana. Interconnection is requested with NorthWestern Energy via the NWMT queue, with an entry date of September 6, 2022. The project's proposed commercial operation date is December 31, 2024.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the 230 kV line between Harlowton and Judith Gap. The project consists of 50 MW of solar generation capacity.
Generated from interconnection queue and public data sources
State
MT
County
Wheatland
Grid Region
Mountain West
Market
—
Developer
—
Utility
NorthWestern Energy
Entity
NWMT
Service Type
—
Point of Interconnection
230 kV line between Harlowton and Judith Gap
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project NWMT-431