NWMT-441
12 MW generation in Lewis And Clark, MT · In queue since January 2023 · Proposed COD December 2023
12 MW
Capacity
1
Components
Gas
3y 4m
In Queue
System Impact Study
IA Status
COD target: 2023
Total Duration
11 months
Schedule
28 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-12-31
NWMT-441 is a proposed 12 MW gas-fired generation project located in Lewis and Clark County, Montana. The project is listed in the NorthWestern Energy (NWMT) interconnection queue with an entry date of January 25, 2023. Its proposed commercial operation date is December 31, 2023.
The project's interconnection status is currently in the System Impact Study phase. The point of interconnection (POI) is the Helena Airport.
Generated from interconnection queue and public data sources
State
MT
County
Lewis And Clark
Grid Region
Mountain West
Market
—
Developer
—
Utility
NorthWestern Energy
Entity
NWMT
Service Type
—
Point of Interconnection
Helena Airport
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project NWMT-441