Queue ID
NWMT-463
Capacity
0.5 MW
Technology
Gas
Status
active
Location
Beadle, SD
Region
West
Developer
IA Status

NWMT-463

NWMT-463BetaActiveGasNWMTLBNL

0.5 MW generation in Beadle, SD · In queue since June 2024 · Proposed COD March 2025

0.5 MW

Capacity

1

Components

Gas

1y 11m

In Queue

IA Status

COD target: 2025

Interconnection

Total Duration

9 months

Schedule

13 months past proposed COD

Pre-Study0%
Queue EntryJun 5, 2024

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-03-31

About

NWMT-463 is a proposed 0.5 MW gas-fired generation project located in Beadle County, South Dakota. The project is listed in the NorthWestern Energy (NWMT) interconnection queue with a queue entry date of June 5, 2024. The proposed commercial operation date is March 31, 2025.

The project is interconnecting to the Huron Substation. As of the latest data, the project's interconnection agreement (IA) status is not specified. The developer is listed as NWMT.

Generated from interconnection queue and public data sources

Project Details

State

SD

County

Beadle

Grid Region

Mountain West

Market

Developer

Utility

NorthWestern Energy

Entity

NWMT

Service Type

Point of Interconnection

Huron Substation

Data Source

LBNL

Market Context
Approximate
ISO / RTO
MOUNTAIN_WEST
Trading Hub
MID-C
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.