NWMT-465
150 MW generation in Stillwater, MT · In queue since June 2024 · Proposed COD December 2029
150 MW
Capacity
1
Components
Gas
1y 11m
In Queue
—
IA Status
COD target: 2029
Total Duration
5y 6m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-12-31
NWMT-465 is a proposed 150 MW gas-fired generation project located in Stillwater County, Montana. The project is listed in the NorthWestern Energy (NWMT) interconnection queue with an entry date of June 7, 2024. The proposed commercial operation date is December 31, 2029, and the point of interconnection is the Rapelje Substation.
The project is currently listed as active in the interconnection queue. No interconnection agreement (IA) status is available. The developer is unknown.
Generated from interconnection queue and public data sources
State
MT
County
Stillwater
Grid Region
Mountain West
Market
—
Developer
—
Utility
NorthWestern Energy
Entity
NWMT
Service Type
—
Point of Interconnection
Rapelje Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project NWMT-465