Hills Solar
20 MW generation in Herkimer, NY · In queue since November 2025
20 MW
Capacity
0
Components
6 months
In Queue
—
IA Status
Total Duration
6 months
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
Hills Solar is a proposed 20 MW solar generation project located in Herkimer County, New York. Developed by SunEast Hills Solar LLC, the project is listed in the New York Independent System Operator (NYISO) interconnection queue as entry NYISO-0581, with a queue entry date of November 26, 2025. The proposed point of interconnection is the Fairfield - Inghams 115kV line.
The project is currently listed as active in the NYISO queue. There is no proposed commercial operation date or interconnection agreement (IA) status available in the provided data. The project is interconnected with utility NM-NG.
Generated from interconnection queue and public data sources
State
NY
County
Herkimer
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
SunEast Hills Solar LLC
Utility
NM-NG
Entity
NYISO
Service Type
—
Point of Interconnection
Fairfield - Inghams 115kV
Data Source
Live · NYISO
- ISO / RTO
- NYISO
- Trading Hub
- ZONE E
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Hills Solar