Dog Corners Solar
20 MW generation in Cayuga, NY · In queue since November 2025
20 MW
Capacity
0
Components
6 months
In Queue
—
IA Status
Total Duration
6 months
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
The Dog Corners Solar project is a proposed 20 MW solar generation facility located in Cayuga County, New York. The project, developed by Dog Corners Solar NY LLC, is listed in the New York Independent System Operator (NYISO) interconnection queue as entry NYISO-0584, with a queue entry date of November 25, 2025. The point of interconnection is the Aurora 34.5kV substation, and the project is currently listed as active in the queue.
The Dog Corners Solar project is linked with 82% confidence to the existing SunEast Dog Corners Solar Project operating plant (EIA ID 62823). The proposed project is interconnected with New York State Electric and Gas (NYSEG). The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
NY
County
Cayuga
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Dog Corners Solar NY LLC
Utility
NYSEG
Entity
NYISO
Service Type
—
Point of Interconnection
Aurora 34.5kV
Data Source
Live · NYISO
- ISO / RTO
- NYISO
- Trading Hub
- NYISO Zone B
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Dog Corners Solar