Clear View Solar (NYISO-1003) — Project Summary

Queue ID
NYISO-1003
Capacity
20 MW
Technology
Solar
Status
active
Location
Steuben, NY
Region
NYISO
Developer
Clear View LLC
IA Status
Facility Study

Clear View Solar

NYISO-1003BetaActiveSolarNYISOLBNL + Live

20 MW generation in Steuben, NY · In queue since April 2020 · Proposed COD December 2025

20 MW

Capacity

1

Components

Solar

6y 1m

In Queue

Facility Study

IA Status

COD target: 2025

Interconnection

Total Duration

5y 8m

Schedule

5 months past proposed COD

Facilities Study50%
Queue EntryApr 6, 2020

Interconnection request submitted to ISO/RTO

TCS StudyCurrent

NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.

Typical: >42 months (historical); ~24 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-12-01

About

Clear View Solar is a proposed 20 MW solar generation project located in Steuben County, New York. Developed by Clear View LLC, the project consists of 20 MW of solar photovoltaic generation. It is interconnected to the New York Independent System Operator (NYISO) queue as project number NYISO-1003, with an initial queue entry date of April 6, 2020. The proposed commercial operation date is December 1, 2025, and its interconnection agreement status is currently in the Facility Study phase.

The proposed project is linked to an existing operating facility, Clear View Solar (EIA plant ID 65931), with a match confidence of 83%. The point of interconnection is the Eelpot Road 34.5 kV line, and the interconnecting utility is New York State Electric and Gas (NYSEG). The project has appeared in recent news coverage.

Generated from interconnection queue and public data sources

Project Details

State

NY

County

Steuben

Grid Region

NYISO (New York)

Market

ISO/RTO Member

Developer

Clear View LLC

Utility

NYSEG

Entity

NYISO

Service Type

Point of Interconnection

Eelpot Road 34.5 kV

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
NYISO
Trading Hub
NYISO Zone B
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.