NYC Energy LLC - Phase 2
220.1 MW storage in Kings, NY · In queue since April 2020 · Proposed COD June 2027
220.1 MW
Capacity
1
Components
Battery
6y 1m
In Queue
System Impact Study
IA Status
COD target: 2027
Total Duration
7y 2m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-06-01
NYC Energy LLC - Phase 2 is a proposed 220.1 MW battery storage project located in Kings County, New York. The developer is NYC Energy, and the interconnecting utility is ConEd. This project is listed in the NYISO interconnection queue as queue ID NYISO-1007, with an entry date of April 22, 2020, and a proposed commercial operation date of June 1, 2027. The project's interconnection status is currently in the System Impact Study phase.
The proposed project is linked to the existing NISA Electric Generation Project operating plant (EIA plant ID 61331). NYC Energy LLC - Phase 2 has been mentioned in recent news coverage.
Generated from interconnection queue and public data sources
State
NY
County
Kings
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
NYC Energy
Utility
ConEd
Entity
NYISO
Service Type
—
Point of Interconnection
Hudson Ave 138 kV
Data Source
LBNL + Live
- ISO / RTO
- NYISO
- Trading Hub
- NYISO Zone J
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- 24152
- POI Substation
- NYPA_KENT_____GT
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about NYC Energy LLC - Phase 2