Morris Solar
20 MW generation in St. Lawrence, NY · In queue since January 2021 · Proposed COD December 2025
20 MW
Capacity
1
Components
Solar
5y 4m
In Queue
Facility Study
IA Status
COD target: 2025
Total Duration
4y 11m
Schedule
5 months past proposed COD
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-01
Morris Solar is a proposed 20 MW solar generation project located in St. Lawrence County, New York. Developed by SED NY Holdings LLC, the project is listed in the New York Independent System Operator (NYISO) interconnection queue as entry NYISO-1039. The project entered the queue on January 6, 2021, and has a proposed commercial operation date of December 1, 2025. Its interconnection status is currently in the Facility Study phase.
The point of interconnection for Morris Solar is the Battle Hill - Balmat 115kV line. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
NY
County
St. Lawrence
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
SED NY Holdings LLC
Utility
NM-NG
Entity
NYISO
Service Type
—
Point of Interconnection
Battle Hill - Balmat 115kV
Data Source
LBNL + Live
- ISO / RTO
- NYISO
- Trading Hub
- ZONE D
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Morris Solar