Transit Solar (NYISO-1051) — Project Summary

Queue ID
NYISO-1051
Capacity
20 MW
Technology
Solar
Status
active
Location
Genesee, NY
Region
NYISO
Developer
SED NY Holding LLC
IA Status
Facility Study

Transit Solar

NYISO-1051BetaActiveSolarNYISOLBNL + Live

20 MW generation in Genesee, NY · In queue since July 2020 · Proposed COD December 2025

20 MW

Capacity

1

Components

Solar

5y 10m

In Queue

Facility Study

IA Status

COD target: 2025

Interconnection

Total Duration

5y 5m

Schedule

5 months past proposed COD

Facilities Study50%
Queue EntryJul 21, 2020

Interconnection request submitted to ISO/RTO

TCS StudyCurrent

NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.

Typical: >42 months (historical); ~24 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-12-01

About

The proposed Transit Solar project is a 20 MW solar generation project located in Genesee County, New York. Developed by SED NY Holding LLC, the project consists of 20 MW of solar photovoltaic generation. It is listed in the New York Independent System Operator (NYISO) interconnection queue as project number NYISO-1051, with an entry date of July 21, 2020. The proposed commercial operation date is December 1, 2025, and the project's interconnection status is currently in the Facility Study phase.

The proposed project is interconnected to the S.E Batavia - Golah 115kV point of interconnection. The project has appeared in recent news coverage.

Generated from interconnection queue and public data sources

Project Details

State

NY

County

Genesee

Grid Region

NYISO (New York)

Market

ISO/RTO Member

Developer

SED NY Holding LLC

Utility

NM-NG

Entity

NYISO

Service Type

Point of Interconnection

S.E Batavia - Golah 115kV

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
NYISO
Trading Hub
ZONE B
Hub Confidence
MEDIUM

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Transit Solar