Mineral Basin Solar Power
401.6 MW generation in Clearfield, PA · In queue since August 2020 · Proposed COD May 2028
401.6 MW
Capacity
1
Components
Solar
5y 9m
In Queue
System Impact Study
IA Status
COD target: 2028
Total Duration
7y 9m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-05-01
Mineral Basin Solar Power is a proposed solar generation project located in Clearfield County, Pennsylvania. The project, developed by Mineral Basin Solar Power, LLC, has a total capacity of 401.6 MW. It is listed in the NYISO interconnection queue as entry NYISO-1080, with a queue entry date of August 21, 2020, and a proposed commercial operation date of May 1, 2028. The project's interconnection status is currently in the System Impact Study phase.
The proposed project is linked to the existing Mineral Basin Solar Power operating plant (EIA ID 67378). Recent news coverage indicates interest in the project, with articles focusing on regulatory and industry aspects.
Generated from interconnection queue and public data sources
State
PA
County
Clearfield
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Mineral Basin Solar Power, LLC
Utility
NYSEG
Entity
NYISO
Service Type
—
Point of Interconnection
Homer City - Mainesburg 345KV
Data Source
LBNL + Live
- ISO / RTO
- NYISO
- Trading Hub
- NYISO Zone A
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-14