East Fishkill
205 MW storage in Dutchess, NY · In queue since December 2020 · Proposed COD November 2028
205 MW
Capacity
1
Components
Battery
5y 5m
In Queue
System Impact Study
IA Status
COD target: 2028
Total Duration
7y 11m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-11-01
The East Fishkill project is a proposed 205 MW battery storage development in Dutchess County, New York. Developed by Microgrid Networks, LLC, the project consists of 205 MW of battery capacity. It is currently active in the NYISO interconnection queue as entry NYISO-1122, with a queue entry date of December 11, 2020. The proposed commercial operation date is November 1, 2028, and the project's interconnection status is currently in the System Impact Study phase.
The proposed project would interconnect to the Central Hudson Gas & Electric (CHG&E) grid at the Shenandoah 115kV point of interconnection. The East Fishkill project has been mentioned in recent industry news.
Generated from interconnection queue and public data sources
State
NY
County
Dutchess
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Microgrid Networks, LLC
Utility
CHG&E
Entity
NYISO
Service Type
—
Point of Interconnection
Shenandoah 115kV
Data Source
LBNL + Live
- ISO / RTO
- NYISO
- Trading Hub
- ZONE G
- Hub Confidence
- HIGH
- POI Substation
- North Shenandoah Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about East Fishkill