Hoffman Falls Wind
72 MW generation in Madison, NY · In queue since January 2021 · Proposed COD December 2027
72 MW
Capacity
1
Components
Wind
5y 4m
In Queue
—
IA Status
COD target: 2027
Total Duration
6y 11m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-01
The Hoffman Falls Wind project is a proposed 72 MW wind generation facility in Madison County, New York. The project, developed by Liberty Renewables Inc., is currently active in the NYISO interconnection queue as entry NYISO-1130, with a queue entry date of January 27, 2021. The proposed commercial operation date is December 1, 2027.
The project consists of 72 MW of wind generation capacity and interconnects at the Cortland - Fenner 115kV Line #3. The Hoffman Falls Wind project has been the subject of recent news coverage.
Generated from interconnection queue and public data sources
State
NY
County
Madison
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Liberty Renewables Inc.
Utility
NM-NG
Entity
NYISO
Service Type
—
Point of Interconnection
Cortland - Fenner 115kV Line #3
Data Source
LBNL + Live
- ISO / RTO
- NYISO
- Trading Hub
- ZONE C
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Hoffman Falls Wind