97 MW generation in Cayuga, NY · In queue since March 2021 · Proposed COD December 2027
97 MW
Capacity
1
Components
Wind
5y 2m
In Queue
System Impact Study
IA Status
COD target: 2027
Total Duration
6y 9m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-01
Agricola Wind is a proposed 97 MW wind energy project located in Cayuga County, New York. The development project, sponsored by Liberty Renewables Inc., is interconnected to the NYSEG utility via the Milliken to Wright Ave 115 kV line #973. It is currently in the System Impact Study phase of the NYISO interconnection queue as project number NYISO-1148, with an original queue entry date of March 10, 2021.
The proposed commercial operation date for Agricola Wind is December 1, 2027. Recent news coverage indicates ongoing development activity related to the project.
Generated from interconnection queue and public data sources
State
NY
County
Cayuga
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Liberty Renewables Inc.
Utility
NYSEG
Entity
NYISO
Service Type
—
Point of Interconnection
Milliken to Wright Ave 115 kV line #973
Data Source
LBNL + Live
- ISO / RTO
- NYISO
- Trading Hub
- ZONE C
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26