Agricola Wind (NYISO-1148) — Project Summary

Queue ID
NYISO-1148
Capacity
97 MW
Technology
Wind
Status
active
Location
Cayuga, NY
Region
NYISO
Developer
Liberty Renewables Inc.
IA Status
System Impact Study

Agricola Wind

NYISO-1148BetaActiveWindNYISOLBNL + Live

97 MW generation in Cayuga, NY · In queue since March 2021 · Proposed COD December 2027

97 MW

Capacity

1

Components

Wind

5y 2m

In Queue

System Impact Study

IA Status

COD target: 2027

Status
as of 21 months ago
Latest milestonefiling application for siting permit · 2024-10-31Fingerlakes1.com · 2024-08-27
Interconnection

Total Duration

6y 9m

Impact Study25%
Queue EntryMar 10, 2021

Interconnection request submitted to ISO/RTO

TCS StudyCurrent

NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.

Typical: >42 months (historical); ~24 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-12-01

About

Agricola Wind is a proposed 97 MW wind energy project located in Cayuga County, New York. The development project, sponsored by Liberty Renewables Inc., is interconnected to the NYSEG utility via the Milliken to Wright Ave 115 kV line #973. It is currently in the System Impact Study phase of the NYISO interconnection queue as project number NYISO-1148, with an original queue entry date of March 10, 2021.

The proposed commercial operation date for Agricola Wind is December 1, 2027. Recent news coverage indicates ongoing development activity related to the project.

Generated from interconnection queue and public data sources

Project Details

State

NY

County

Cayuga

Grid Region

NYISO (New York)

Market

ISO/RTO Member

Developer

Liberty Renewables Inc.

Utility

NYSEG

Entity

NYISO

Service Type

Point of Interconnection

Milliken to Wright Ave 115 kV line #973

Data Source

LBNL + Live

DeveloperAgricola Wind LLCFingerlakes1.com · 2024-08-27
Market Context
Approximate
ISO / RTO
NYISO
Trading Hub
ZONE C
Hub Confidence
MEDIUM

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

News & Articles (1)Beta

Last updated 2026-03-26

View all articles

No ask pi reports yet for this entity.