York Run Solar
90 MW generation in Chautauqua, NY · In queue since March 2021 · Proposed COD August 2026
90 MW
Capacity
1
Components
Solar
5y 2m
In Queue
System Impact Study
IA Status
COD target: 2026
Total Duration
5y 5m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-08-01
York Run Solar is a proposed 90 MW solar generation project located in Chautauqua County, New York. The project, developed by York Run Solar, LLC, is interconnected to the NYISO grid under queue ID NYISO-1151. It entered the queue on March 18, 2021, and has a proposed commercial operation date of August 1, 2026. The project's interconnection status is currently in the System Impact Study phase.
The proposed project is linked to the existing York Run Solar operating plant (EIA ID 68585). Recent news coverage has discussed the development.
Generated from interconnection queue and public data sources
State
NY
County
Chautauqua
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
York Run Solar, LLC
Utility
NM-NG
Entity
NYISO
Service Type
—
Point of Interconnection
Falconer - Warren 115 kV line #171
Data Source
LBNL + Live
- ISO / RTO
- NYISO
- Trading Hub
- NYISO Zone A
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about York Run Solar