BR Benson Mines Solar
12.1 MW generation in St. Lawrence, NY · In queue since May 2021 · Proposed COD October 2026
12.1 MW
Capacity
1
Components
Solar
5 years
In Queue
Facility Study
IA Status
COD target: 2026
Total Duration
5y 5m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-10-01
The BR Benson Mines Solar project is a proposed 12.1 MW solar generation project located in St. Lawrence County, New York. Developed by BR Project 1 LLC, the project is interconnected within the New York Independent System Operator (NYISO) queue as entry NYISO-1166. The project entered the queue on May 7, 2021, and has a proposed commercial operation date of October 1, 2026. Its interconnection status is currently in the Facility Study phase, and the point of interconnection is the Brown's Falls to Newton Falls #22 34.5kV Line.
The proposed project consists of 12.1 MW of solar photovoltaic generation. It is currently listed as an active project within the NYISO interconnection queue. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
NY
County
St. Lawrence
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
BR Project 1 LLC
Utility
NM-NG
Entity
NYISO
Service Type
—
Point of Interconnection
Brown's Falls to Newton Falls #22 34.5kV Line
Data Source
LBNL + Live
- ISO / RTO
- NYISO
- Trading Hub
- ZONE D
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about BR Benson Mines Solar