NY125A - Fort Covington Solar
250 MW generation in Franklin, NY · In queue since May 2021 · Proposed COD August 2027
250 MW
Capacity
1
Components
Solar
5 years
In Queue
System Impact Study
IA Status
COD target: 2027
Total Duration
6y 3m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-08-01
NY125A - Fort Covington Solar is a proposed solar generation project with a total capacity of 250 MW. The project is located in Franklin County, New York, and is being developed by Fort Covington Solar LLC. It is interconnected to the NYISO grid at the Moses-Willis 230 kV (MW1) point of interconnection and has appeared in recent news coverage.
The project is listed in the NYISO interconnection queue as queue ID NYISO-1183, with an entry date of May 20, 2021. Its proposed commercial operation date is August 1, 2027. The project's interconnection status is currently in the System Impact Study phase.
Generated from interconnection queue and public data sources
State
NY
County
Franklin
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Fort Covington Solar LLC
Utility
NYPA
Entity
NYISO
Service Type
—
Point of Interconnection
Moses-Willis 230 kV (MW1)
Data Source
LBNL + Live
- ISO / RTO
- NYISO
- Trading Hub
- ZONE D
- Hub Confidence
- MEDIUM