ELP Granby Solar II
20 MW hybrid in Oswego, NY · In queue since February 2022 · Proposed COD December 2026
20 MW
Capacity
1
Components
Solar
4y 3m
In Queue
Facility Study
IA Status
COD target: 2026
Total Duration
4y 10m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-01
The ELP Granby Solar II project is a proposed 20 MW hybrid solar and battery energy storage project located in Oswego County, New York. The developer is ELP Granby Solar II LLC. The project consists of 20 MW of solar generation.
The project is listed in the NYISO interconnection queue as queue ID NYISO-1329, with an entry date of February 11, 2022, and a proposed commercial operation date of December 1, 2026. Its interconnection status is currently in the Facility Study phase.
Generated from interconnection queue and public data sources
State
NY
County
Oswego
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
ELP Granby Solar II LLC
Utility
NM-NG
Entity
NYISO
Service Type
—
Point of Interconnection
Curtis Street - Teall 115 kV
Data Source
LBNL + Live
- ISO / RTO
- NYISO
- Trading Hub
- ZONE C
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about ELP Granby Solar II