Wulf Compute Data Center II
250 MW generation in Niagara, NY · In queue since March 2025
250 MW
Capacity
0
Components
1y 2m
In Queue
—
IA Status
Total Duration
1y 2m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
The proposed Wulf Compute Data Center II project is a 250 MW generation project located in Niagara County, New York. The project, developed by TeraWulf Brookings LLC, is listed in the NYISO interconnection queue as queue ID NYISO-1732, with a queue entry date of March 29, 2025. The point of interconnection is the Kintigh 345kV sub-station, and the project's technology is categorized as "Other" with a technology detail of "L".
The Wulf Compute Data Center II project is currently listed as "active" in the NYISO queue. The project has been the subject of recent news coverage, with eight articles categorized as industry news, deals, and regulatory matters.
Generated from interconnection queue and public data sources
State
NY
County
Niagara
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
TeraWulf Brookings LLC
Utility
NYSEG
Entity
NYISO
Service Type
—
Point of Interconnection
Kintigh 345kV sub-station
Data Source
Live · NYISO
- ISO / RTO
- NYISO
- Trading Hub
- ZONE A
- Hub Confidence
- HIGH
- POI Substation
- Keith Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26