Broome County Tech Park
250 MW generation in Broome, NY · In queue since October 2025
250 MW
Capacity
0
Components
7 months
In Queue
—
IA Status
Total Duration
7 months
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
The Broome County Tech Park is a proposed 250 MW generation project located in Broome County, New York. The project, developed by The Agency, is listed in the NYISO interconnection queue as entry NYISO-1752, with a queue entry date of October 30, 2025. The proposed point of interconnection (POI) is a 345 kV connection via a loop on the existing Oakdale-Fraser Line 32, with the interconnection substation planned to have a ring bus configuration. The project's technology is categorized as "Other" with the detail "L".
This development project is currently active in the NYISO queue. The project has been the subject of recent news coverage, with 21 articles categorized as regulatory and industry news.
Generated from interconnection queue and public data sources
State
NY
County
Broome
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
The Agency
Utility
NYSEG
Entity
NYISO
Service Type
—
Point of Interconnection
345 kV POI via a loop on the existing Oakdale-Fraser Line 32. The interconnection substation will have a ring bus configuration.
Data Source
Live · NYISO
- ISO / RTO
- NYISO
- Trading Hub
- ZONE C
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-14