Kenwood Tech Center
180 MW generation in Albany, NY · In queue since November 2025
180 MW
Capacity
0
Components
6 months
In Queue
—
IA Status
Total Duration
6 months
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
The Kenwood Tech Center is a proposed 180 MW generation project located in Albany County, New York. The project, developed by EKG Group LLC, is interconnected to National Grid via the Albany?Bethlehem 115 kV Line #18. It is listed in the NYISO interconnection queue as entry NYISO-1754, with a queue entry date of November 11, 2025. The project's technology is listed as "Other" with a detail of "L," and its interconnection status is currently active.
The proposed project is listed in the NYISO interconnection queue, but no proposed commercial operation date or Interconnection Agreement (IA) status is available in the provided data. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
NY
County
Albany
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
EKG Group LLC
Utility
National Grid
Entity
NYISO
Service Type
—
Point of Interconnection
Albany?Bethlehem 115 kV Line #18
Data Source
Live · NYISO
- ISO / RTO
- NYISO
- Trading Hub
- ZONE F
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Kenwood Tech Center