Site Master Plan Expansion Phase I
45 MW generation in Albany, NY · In queue since December 2025
45 MW
Capacity
0
Components
5 months
In Queue
—
IA Status
Total Duration
5 months
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
The Site Master Plan Expansion Phase I is a proposed 45 MW generation project located in Albany County, New York. The project, developed by the Research Foundation of SUNY, is interconnected to National Grid and is listed in the NYISO interconnection queue as entry NYISO-1755, with a queue entry date of December 18, 2025. The project's technology is listed as "Other" with a technology detail of "L".
The project is currently listed as "active" in the interconnection queue. The proposed point of interconnection (POI) is at Patroon Creek and McKnownville.
Generated from interconnection queue and public data sources
State
NY
County
Albany
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Research Foundation of SUNY
Utility
National Grid
Entity
NYISO
Service Type
—
Point of Interconnection
Patroon Creek and McKnownville
Data Source
Live · NYISO
- ISO / RTO
- NYISO
- Trading Hub
- ZONE F
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Site Master Plan Expansion Phase I