Canisteo Wind (NYISO-519) — Project Summary

Queue ID
NYISO-519
Capacity
289.8 MW
Technology
Wind
Status
active
Location
Steuben, NY
Region
NYISO
Developer
Canisteo Wind Energy LLC
IA Status
Facility Study

Canisteo Wind

NYISO-519BetaActiveWindNYISOLBNL

289.8 MW generation in Steuben, NY · In queue since November 2015 · Proposed COD December 2027

289.8 MW

Capacity

1

Components

Wind

10y 6m

In Queue

Facility Study

IA Status

COD target: 2027

Interconnection

Total Duration

12y 1m

Facilities Study50%
Queue EntryNov 2, 2015

Interconnection request submitted to ISO/RTO

TCS StudyCurrent

NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.

Typical: >42 months (historical); ~24 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-12-01

About

The Canisteo Wind project is a proposed wind energy generation project located in Steuben County, New York. The project, developed by Canisteo Wind Energy LLC, has a total capacity of 289.8 MW. It is interconnected to the New York Independent System Operator (NYISO) queue under queue ID NYISO-519, with an entry date of November 2, 2015. The proposed commercial operation date is December 1, 2027, and its interconnection status is currently in the Facility Study phase.

The proposed project is linked to the existing Canisteo Wind Farm (EIA plant ID 62947). The project has been the subject of recent news coverage.

Generated from interconnection queue and public data sources

Project Details

State

NY

County

Steuben

Grid Region

NYISO (New York)

Market

ISO/RTO Member

Developer

Canisteo Wind Energy LLC

Utility

NYSEG

Entity

NYISO

Service Type

Point of Interconnection

Bennett 115kV

Data Source

LBNL

DeveloperInvenergyHornell Evening Tribune · 2019-02-05
TransactionPPAHornell Evening Tribune · 2019-02-05
OfftakerNew York Power AuthorityHornell Evening Tribune · 2019-02-05
PPA structurePhysicalHornell Evening Tribune · 2019-02-05
PPA term20 yearsHornell Evening Tribune · 2019-02-05
Market Context
Approximate
ISO / RTO
NYISO
Trading Hub
ZONE B
Hub Confidence
HIGH
Nearest Node (Estimated)
DUNKIRK__115KV_TB_200
POI Substation
Bennett Road Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

News & Articles (1)Beta

Last updated 2026-03-26

View all articles

No ask pi reports yet for this entity.

ask pi about Canisteo Wind