Bull Run II Wind
449 MW generation in Clinton, NY · In queue since December 2015 · Proposed COD December 2026
449 MW
Capacity
1
Components
Wind
10y 5m
In Queue
Facility Study
IA Status
COD target: 2026
Total Duration
11 years
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-01
The Bull Run II Wind project is a proposed 449 MW wind generation facility in Clinton County, New York. The project, developed by Bull Run Energy LLC, is interconnected to the NYISO grid at the Patnode-Duley, Ryan-Plattsburgh 230kV point of interconnection. It is listed in the NYISO interconnection queue as queue ID NYISO-521, with an entry date of December 15, 2015.
The proposed commercial operation date for the Bull Run II Wind project is December 1, 2026. Its interconnection status is currently in the Facility Study phase. The utility involved is NYPA. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
NY
County
Clinton
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Bull Run Energy LLC
Utility
NYPA
Entity
NYISO
Service Type
—
Point of Interconnection
Patnode-Duley, Ryan-Plattsburgh 230kV
Data Source
LBNL
- ISO / RTO
- NYISO
- Trading Hub
- ZONE D
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Bull Run II Wind