Riverhead Solar 2
36 MW generation in Suffolk, NY · In queue since February 2016 · Proposed COD January 2027
36 MW
Capacity
1
Components
Solar
10y 3m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
10y 11m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-01-01
Riverhead Solar 2 is a proposed 36 MW solar generation project located in Suffolk County, New York. The project, developed by Riverhead Solar 2, LLC, is in the New York Independent System Operator (NYISO) interconnection queue as entry NYISO-535, with a queue entry date of February 23, 2016. The proposed commercial operation date is January 1, 2027. The project's interconnection status is currently in the Facility Study phase.
The proposed project will interconnect to the LIPA grid at the Edwards 138kV point of interconnection. Recent news coverage has discussed the development project.
Generated from interconnection queue and public data sources
State
NY
County
Suffolk
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Riverhead Solar 2, LLC
Utility
LIPA
Entity
NYISO
Service Type
—
Point of Interconnection
Edwards 138kV
Data Source
LBNL
- ISO / RTO
- NYISO
- Trading Hub
- ZONE K
- Hub Confidence
- HIGH
- POI Substation
- Edwards Ferry Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Riverhead Solar 2